Solar Green Energy

2013 10MWp Solar Farm

2013 10MWp Solar Farm

Owner :   Malaysian Solar Resources Sdn Bhd
Client :   Special Universal Sdn Bhd
Location :   Gebeng, Pahang
Capacity :   (Phase 1) 5MWp & (Phase 2) 5MWp
Completion Date :   (Phase 1)22.12.2013 & (Phase 2)15.04.2014
Service :   Design and build solar system on 50 acres land, comprising all the Mechanical and Electrical (M&E/ELV) scopes of works, from DC supply to feed up power line/national grid.

 

Appointed by Malaysian Solar Resources as its electrical contractor to develop a whole new brand solar farm with a capacity of 10MWp, our scope of work included:

  • Design and build for all M&E scope including DC, AC and HT works
  • Design and install complete earthing and lightning protection system
  • Installation and termination of all DC, AC and HT cabling works
  • Installation and termination of AJBs, inverters, transformer and switchgears complete with support structure
  • Installation of ventilation system for inverters
  • Installation of monitoring system for power production
  • Wiring works substation unit (SSU), office and all inverter rooms including ELV works
  • Configuring switchgears and complete inter-locking system within SSU to TNB Pencawang Masuk Utama(PMU)
  • Testing and commissioning of all electrical equipment and system
  • 10MW Solar Farm, Gebeng 2014