2015 1MWp Building Integrated Photovoltaic (BIPV)
Owner : |
|
Malaysian Solar Resources Sdn Bhd |
Client : |
|
PS Green Sdn Bhd |
Location : |
|
Kuala Berang, Terengganu |
Capacity : |
|
1MWp |
Completion Date : |
|
30.12.2015 |
Service : |
|
Design and build solar system on building elevated structure, comprising all the Mechanical and Electrical (M&E/ELV) scopes of works, from DC supply to feed up power line/national grid.
|
Appointed by Malaysian Solar Resources as its electrical contractor to develop a whole new brand solar farm with a capacity of 1MWp, our scope of work included:
Design and build for all M&E scope including DC, AC and HT works
Design and install complete earthing and lightning protection system
Installation and termination of all DC, AC and HT cabling works
Installation and termination of AJBs, inverters, transformer and switchgears
Installation of BIPV solar mounting structures and solar panels.
Installation of Solar mounting structures and solar panels.
Installation of monitoring system for power production
Wiring works and installation of 11kv compact sub-station and all inverter including ELV works
Configuring switchgears and complete inter-locking system within 11kv CSSU to TNB sub-station.
Testing and commissioning of all electrical equipment and system